Major construction work is now finished and the Church Point Reserve Carpark has been restored

As you are aware, Ausgrid has been installing a new electricity cable between Church Point and Scotland Island. This cable will improve the reliability of the power supply to Scotland Island.

Progress to date

The major construction work is now complete and the Church Point Reserve Carpark has been restored and returned to the community. Ausgrid would like to thank you for your ongoing patience while we completed this important work.

In early 2021, we will need to connect the new cable to our network. There will be little impact to the carpark or community. We will notify you before we do this work.

Parking at Church Point Reserve Carpark

The parking restrictions in the Church Point Reserve Carpark have now been removed.

We would like to thank those residents who volunteered to move their cars to Rowland Reserve for the duration of the project. We will be in contact with you over the coming weeks to confirm your final cashback.

You can now, either choose to:

  • Keep your Rowland Reserve parking permit and use it until 31 August 2021 to park in the Rowland Reserve Carpark only; or
  • Return your Rowland Reserve parking permit to Council’s Customer Service Centre at Mona Vale* and apply for a Church Point parking permit (see overleaf for further details).

Keeping you informed

For information related to the project visit our website at www.ausgrid.com.au/scotlandisland. Alternatively, you can contact Ausgrid on 1800 604 765 or at majorprojects@ausgrid.com.au.

We apologise for any inconvenience this work may have caused and thank you for your continued patience as we work to improve network reliability in the area.

Scotland Island RP Update - 201218 Scotland Island RP Update - 201218 (135 KB)



 

Upcoming Events
20-Mar-2021 Jammin in the Bays